Impactor Borewell Rubber Crawler Mounted Drill Rig With 200 Meters Depth For Borehole Blasting
ST 200 Crawler Mounted Drill Rig Introduction
High quality, competitive price, 200 m drilling rig depth ,crawler assembly, powerful, variety terrain, stable operation, flexible volume, driven by hydraulic motor, large traction, various models, support customization.Pneumatic drilling rig is especially suitable for water intake in mountainous and rocky strata
ST 200 Crawler Mounted Drill Rig Parameters
Drilling Rig Model | ST-200 |
Weight | 5.8T |
Bore diameter | 140-305mm |
Drilling depth | 200m |
Stroke | 3.4m |
Travelling speed | 2.5km/h |
Gradeability | 30% |
Power | 65-70KW |
Rated pressure | 1.7-3.0mpa |
Air consumption | 17-30m³/min |
Drill rod diameter | Φ76, Φ89 |
Drill rod length | 1.5m 2.0m 3.0m |
Elevating capacity | 15T |
Swing speed | 45-70rpm |
Swing torque | 3500-4800N.M |
Dimensions | 4000*1750*2450mm |
ST 200 Crawler Mounted Drill Rig Features:
ST 200 Crawler Mounted Drill Rig Service:
Before sales: Engineering Consultance Service & Technical
Support;
After sales: Process clients' feedback and or problems during the
operation of the machines within 24 hours;
OEM service: We accept OEM orders and 70 percent of our clients are
enjoying OEM services;
Specific requirements for drilling equipment installation
1. The length, quantity, and foundation type of various machine logs should be determined based on the type of equipment, drilling design angle, depth, and regional conditions.
2. Regardless of the use of wooden bases, channel steel, or I-beam machines, their layout requirements are stable, square, and horizontal. The cross connecting bolts of each part should be equipped with washers and tightened with nuts to increase the bearing capacity of the foundation and the stability of the equipment;
3. In deep pit construction, if the foundation rock layer is not firm, concrete foundation should be poured into the four legs of the drilling tower, drilling rig, power machine, and lower excavation pit.
4. The installation sequence of drilling equipment is the drilling rig (intermediate shaft), power machine, mud pump, and other auxiliary equipment;
5. The bolts of the drilling rig and power machine base are integrated with the intersection of the machine bed wood and machine sleepers;
6. Install the drilling rig so that the center of the crown block (or leading edge), the center of the vertical shaft (or center of the rotary table), and the center of the drilling hole are in a straight line;
7. When installing the intermediate shaft, power machine, and mud pump, if belt transmission is used, the distance between each part should be appropriate, and the belt pulley should be aligned;
8. The installation of bolts for various equipment and auxiliary equipment must be equipped with washers and tightened;
9. After the installation of various equipment is completed, the team must organize relevant personnel for inspection and acceptance. Only after the installation quality and safety protection devices meet the requirements can drilling be started.
Jinzhou City Shitan Machinery Equipment CO. LTD.
Jinzhou City Shitan Machinery Equipment CO. LTD. is a professional production and
processing company for core drilling rigs, crawler drilling rigs, various track chassis, various
types of mud pumps, various track transport vehicles, etc. It is one of the outstanding
manufacturers of similar products in North China. Strong technical force. The modern productiona
equipment and complete testing means are specialized in the development, manufacture and
marketing of drilling rigs.
To ensure the quality and stability of the machine, we use the most advanced production and testing
equipment, Made from high quality materials, with fashion and compact design, that keeps our drilling
rigs more efficiency and with low failure rate, more economic and durable, and with a high comprehensive
cost performance. Our water drilling rigs have received the real market validation as the majority of our
customer’s positive feedback.
The company's main products are rigs: XY-1, XY-1A, XY-1B, GK-180, GK-200, DPP-100 and other series
of drilling rigs: gearbox assemblies and gyro assemblies for various rigs, Winch assembly, reducer assembly,
pump assembly. Drilling tools: sedimentary pipe joints, casing joints, casing couplings, drill pipe joints, casing
core pipes, lifters, automatic drop hammers, earth borrowers, standard penetrations, forks, lock joints, alloy drill
bits Hundreds of drilling tools, such as steel sand drill bits, core pipe joints, drill pipe pliers, and casing pliers.
Jinzhou City Shitan Mechinery Equipment CO. LTD. has a complete and scientific quality management
system. The integrity, strength and product quality of Jinzhou Stone Exploration Machinery Co., Ltd. have been
recognized by the industry. Welcome friends from all walks of life come to visit, guide and negotiate business!